CITY OF LOS ANGELES
BUREAU OF SANITATION
PRIVATE WATER SUB-METER COSTS
For 2010/2011

FMD  -   SSC  -   General Info
Com'l / Res'l Submeter


1" AND Smaller Sewer Sub-Meter CostsNOTES below:
#2 Plastic Meter Box w/RPM Cover
     (includes hardware)
- $  60
5/8" X ¾" Meter - $ 235
1" Int. Meter - $ 255
1" Reg. Meter - $ 300
Meter with Box included: ( 5/8" x 3/4") - $ 295
Meter with Box included: ( 1" Int. ) - $ 315
Meter with Box included: ( 1" Reg. ) - $ 360

1 1/2" to 2" Sewer Sub-Meter Costs
#3 Plastic Meter Box w/RPM Cover
    (includes hardware)
- $ 210
1 ½" Meter
    (included 1 ½" flange & valve)
- $ 545
2" Meter
    (included 2" flange & valve)
- $ 690
Meter with Box included: ( 1 1/2" ) - $ 755
Meter with Box included: ( 2" ) - $ 900

Note: The meter must be purchased from DWP and a plumbing permit obtained from and inspection by Building & Safety is required to qualify the property for billing of the sewer service charge under the private water sub-meter program.

DWP at 213 367-2130 has the most current meter information and prices so call to verify.  The larger meters normally require extra hardware and it is reflected in the prices above.

Also see: http://www.ladwp.com/ladwp/cms/ladwp002068.jsp
(Prices are generally in effect until changed.)

Bureau of Sanitation Hotline (to request info packages only) 1 800 540-0952 or 213 473-4181.

Info Packages: (residential) http://www.lacitysan.org/fmd/pdf/submtrres.pdf     -       Installation Summary
(commercial) http://www.lacitysan.org/fmd/submtrcom.htm

    smcosts.htm                 Modified:  7/12/10